BESS Bucharest 01

Bucharest, Romania · 5 MWh · 12.8% gross
Gross yield
12.8%
On capex / yr
Target raise
€1.70M
Opens next quarter
Capacity
5 MWh
2.5 MW · installed
Chemistry
LFP
battery
Pipeline Not yet open
€1.70M
target raise · opens for fundraising next quarter
StatusSite secured, permitting under way
DepositsNot open yet
See a vault that's already running
Yield breakdownShare of gross yield
9.0%1.7%1.4%0.7%
Depositor APY
Yield paid out to vault depositors
9.0%
Protocol Fee
Operations & protocol treasury
1.7%
Sinking Fund
Reserved to refresh batteries & gear after ~10 yrs of degradation
1.4%
Reserve
Operational buffer for downtime events
0.7%
Use of funds
62%18%12%8%
Battery system & PCS€1.05M
Installation & EPC€306K
Grid connection€204K
Contingency€136K
Project details
Power / Energy2.5 MW / 5 MWh
ChemistryLFP
Projected annual revenue€218K
Gross yield on capex12.8%
Receipt tokenmwBUC01 · XRPL MPT
NetworkXRPL · Mainnet
Your position

Connect a wallet to deposit into this vault and track what it earns. Everything on this page is readable without one.